UNITED STATES V. FREEL.
299
UNITED STATES v. FREEL et al. (Circuit Court, E. D. New York. 1.
February 15, 18\)9.)
PIlDfCIPAL A:-1D SURETy-RELEASE OF SUIlETy-AI,TERATTON OF CONTHACT.
2.
Under such a provision, the alteration of the plans and speeifications ilf a c{)ntract for the construction of a dry dock for the United States,
300
92 FEDERAL REPORTER.
in considerll,tion of $612,000, ,so that its length should be 670 rather than 600 feet, with an increased payment of $45,566, and an extension of the time of performance for three months, was within the contemplation of the parties and sureties to the original contract, and the latter were not released thereby. But a supplemental contract cllanging the location of the entire dry dock from the water side, as provided in the initial contract, to a location 64 feet inland, and requiring the contractor to make all necessary excavations and connedions with the water at an increased payment of $5,063.1i'l, and with an increased time for performance, released the sureties, inasmuch as all consent of the sureties anticipating changes. in the contract related to alterations in the attacherl plans and specifications, of which the location of the structure was no part. (Syllabus by the Court.)
This is an action by the United States on the bond of a contractor for the construction of a dry dock at the Brooklyn navy yard. On demurrer to complaint. George H. Pettit and Robert H. Roy, for the united States. James R. Soley and Howard A. Taylor, for defendants. THOMAS, District Judge. The question presented on this demurrer is whether the sureties of a contractor, who undertook by contract concluded with the United States, on the 17th November, 1892, in consideration of $612,000, to build a dry dock, "to be located nt such place on the water line of the navy yard, Brooklyn, K. Y., as shall be designated," are relieved from liability by reason of a chang-c of such contract by a supplemental agreement concluded between the contractor and the United States, on the 16th day of June, 1893, whereby it was stipulated that the dry dock should be extended to the length of 670 feet, which was 70 feet in excess of the length as originally provided, at an agreed price of $45,556, whereby also "the time fixed in the original contract for the completion of the said dry dock shall be extended three (3) months, on account of the extra labor," etc., or are relieved from liability by reason of an agreement concluded on the 17th of August, 1893, between the contractor and the United States, whereby, in consideration of $5,063.18, to be paid the contractor, it was stipulated to "change its location to one sixty-four (64) feet further inland than that laid down and staked out when the said contract was entered into," and whereby the contractor undertook that "he will perform all the additional excavation necessary at the entrance of the dry dock in consequence of the said change of location; also, all the additional work necessary to lengthen the suction pipes provided to .be laid down from the present pump house, including the piping, round piles, sheet piles, timber, iron work, excavation, and back filling, etc., and all other work incident to said change of location, supplying all the labor and materials therefor," whereby also "the time limited by the said contract for the completion of the dry dock shall be extended for a period of eight (8) weeks." The plaintiff answers the contention tllat the supplementary contracts effect the discharge of the sureties by the claim that such contracts made pursuant to the seventh article of the contract, whereby the sureties anticipated such contracts, and consented there-