CHERRY VALLEY IRON WORKS 'V. FLORENCE IRON RIVER CO.
569
reason of the rule of the liability of the master for the servant's negligence, as declared in the Ross Case and interpreted in the Baugh Case, does not consist in the fact that the conductor of the train was the superior officer of the injured servant, but rather in the fact that the latter was in the department of the former; and the conductor was held to be a vice principal, not because he could enforce the obedience of subordinate servants placed under his charge, but because he was clothed with the power to govern the movements of the train which constituted his department. The case of the plaintiff comes within this interpretation of the reason of the rule of those decisions, for he was, at the time of receiving his injury, within the department of the conductor of the train, and subject to his control. The judgment is affirmed, with costs to the defendant in error. CHERRY VALLEY IRON WORKS v. FLORENCE IRON RIVER CO.
(Circuit Court of Appeals, Sixth Circuit. No. 153. 1. CONTRAOT OF' SALE-RESCISSION BY SELLER.
October 29, 1894.)
Defendant contracted to seU to plaintiff a quantity of ore, to be dellvered in seven equal parts in each of seven months, the price to be also paid 'in equal installments in the same months. The contract contained a stipulation that, if plaintiff failed to make any payment for ten days after it was due, defendant should have the right to cancel the contract as to all ore not delivered at the time of such default. Plaintiff made the first three payments, but, not needing all the ore, defendant delivered less than the amount called for by the contract during such three months. Plaintiff failed to make the fourth payment, and defendant refused to ship more ore until the same was made. No more payments were made and no more ore shipped. Held, that the refusal to make further shipments was an exercise of the right reserved to defendant by the aforesaid stipulation in the contract; that this did not amount to an absolute rescission of the contract, entitling both parties to be restored to their original positions, but entitled defendant to treat plaintiff's failure to pay as a breach of the contract, justifying defendant in refusing to continue deliveries, and giving defendant the right to claim damages for such breach, while plaintiff was entitled to a return of the sums paid in excess of the price of the ore actually delivered. Plaintiff made the first two payments in notes, which were accepted by defendant, and offered notes for the third payment, which defendant refused to accept, but agreed to hold for a short time, until plaintiff should take them up in c8.sh. Defendant afterwards negotiated the notes. Held, that defendant was not entitled to treat plaintiff as in default upon such third pa:rment. The ore sold having never been separated from the mass in defendant's possession, and· appropriated to plaintiff, and the title not having passed, the measure of damages for plaintiff's failure to take and pay for the undelivered ore was the difference between the contract price and the market price at the times when the several installments should have been delivered. '
t.
PAYMENT-By NOTES.
8.
SALES-MEASURE OF DAMAGES.
In Error to the Circuit Court of the United States far the Eastern Division of the Northern District of Ohio.
570
FEDERAL< REPOR'rER,
Yolo 64.
This Wiatf ran action by theOherry Valley Iron Works against the FlorettMIl'on River Company. Defendant had judgment, and plainti:ff'bringl!l error. This .was by the plalntl1! In error to recover a sum of money cl8,tmed to be due from 'the defendant by reason, of an overpayment made by: the' plafutifr upon a contract of sale between the defendant, as seller, and the. plaintiff, as buyer, of a quantity of ore from the dE'fendant's mines. The contract was in writing, bearing date August 20, 18\)0. By it the defendant, th,e, l<'lorence Iron, River Company, agreed to sell to the Cherry Valley Iron Works, and the latter company agreed to buy, 10,000' tons of the Florence Iron River Company's ore, of its standard quality, at the price of $3.75 per ton, making $37,500 for the whole purchase. This total sum was to bepald in seven ,equal payments of $5,357.14 each, on the 15th day Of October, November, December, January, February, March, and April following, respectively, and the ore was to be delivered in equal installments during those months, corresponding to the payments. Other stipulations were contained in the contract, but none of them are material to the present controversy, except the one found at the end, which is in the following words: , "And in case said party Of, the second part fails to make any or elthet of the above-named payments for the t)eriod of ten days after the S/Ulle becomes due, said Florence Iron River Company shall have the right to cancel, this contract for all ore not delivered at the time such default is made." The plaintllf made the payments due in October and November by its notes, payable in four months after their date, and payment in that mode· was accepted by the defendant, and credit given for, the amount thereof. In December the plaintiff was again proceeding to make the, payment for that month in tbat way. But while the notes were in the course of transmission to the defendant, the latter notified the plaintiff that it was unwilling to receive that payment by notes, and that it would Insist upon payment In cash. It was, however, agreed tl1at the defendants should hold, the notes until the end of December, and that plaintiff shOUld take them up with cash in the meantime. 'l'hey were not so· taken up, but were negotiated by the defendant, and paid by the plaintiff on their maturing, four months after their date. The plalntlfr, not being ready to receive the ore, did not call for any delivery until November. During that month i31 tons, In December 2,090 tons, and in January 145 tons were delivered. On the 27th day of January, 1891, the plaintiff requested a resumption of shipment at the rate of five cars per day. But it had not made the January payment, and the defendant, on January 29th, refused to ship any more ore until both the December and January payments should be made. Matters continued In that state until April 29, 1891, when, all the payments having become:due, the defendant demamded payment for the unpaid balance of the whole contract price, the balance being $20,665.40. The plaintlfE subsequently offered to pay 25 cents per ton on all the undelivered ore·. to be releas4ffi frOm the contract. This was refused. the market value of the ore haviDg gone down more than 50 cents per ton below the contract price. After April 29th further correspondence ensued during the month of May, and Until the H5th of June. In this eorrespondence the defendant insisted uPOll.the payment Of the contract, price, and threatened that unless payment should be made the undelivered ore would be sold for account of the plaintiff, and the difference between the proceeds and the unpaid. purchase ",puld be charged the plaintiff. On ilia 12th day 0,fMay thlil d, wrote the Pial,ntiff, saying: "AS, our final statement to you, W:e what we have heretofore wrlttencthat we propose to flaIl the ore, to talle, at the best market price, for your account, for the difference." And by letter of May 14th the and hold your defendant repeats this purpose. On June 15th the following letter was addressed by the defendant to the plaintiff: 0., .Tune 15, 1891. J. H. King, Esq., Prest. Cherry Valley Iron Wor'ks,'Palnesvilk, D.-Dear Sir.: We beg to call your attention to the following clause In the contract ·fot: the purchase of ten thousand, . 'i'
i:
,,'
;
I
CHERRY VALLEY IRON WORKS V. FLORENCE IROX RIVER CO.
571
tons Florence ore, entered into by the Florence Iron River Co. and Cherry Valley Iron Works, under date of August 20, 1890: 'And In case the said party of the second part fails to make any or either of the above-named payments for the period of ten days after the same becomes due, said Florence Iron River Co. shall have the right to cancel this contract for all ore not delivered at the time such default iil made,' As your company is in default on several payments under said contract; as in our letters of May 12 and 14, 1891, we give you notlee of what our action would be unless you promptly made the payments then long past due,-we beg to notify you that we have exercised the rights conferred UpOll us in the eontract in accordance with the clause mentioned above, and have canceled the contract for all ore now undelivered. Very truly yours, Tod, Stambaugh & Co., Agts," . Thereupon, the plaintiff demanded of the defendant repayment of the ,sum which it had paid upon the contract in excess of the sum due for the ore delivered at the contract price; such excess being $5,146.27. This being refused, the plaintiff, on July 22, 1891, brought this action to recover 'it. On July 31st, nine days afterwards, the defendant sold the undelivered ore for three dollars per ton, and credited the sum realized to plaintiff's ·account. The account, with this credit entered, showed a balance against the plaintiff of $335.83, for which sum the defendant, in its answer, set up a counterclaim. The case was tried by the court without a jury. The findings of fact were general,-that the plaint;ff was not entitled to recover the excess of payment for which it sued to recover, and that defendant was entitled to recover the aIDount of its counterclaim.. An opinion was filed, stating, in 'part, the facts which the court had found, and its conclusions of law. This opinion was filed on the saIDe day with the filing of the general findings of fact,-August 3, 1894. On the 7th day of September following, '3. motion for a new trial was o"\"erruled, and judgment entered in accordance with the findings, to which the plaintiff excepted. During the trial, objections and exceptions were taken to the admission of each of the several letters above referred to, except that of June 15, 1891. The court, against the plaintiff's objection, received a statement of the account between the parties, as prepared by the defendant's bookkeeper, not to prove the matters therein stated, but as the court's computation, if it should be found correct. The court afterwards adopted the account as correct in the findings in the opinion before referred to, and it appears to form the basis of the judgment. The plaintiff also objected, upon the trial, to the evidence of the resale of the undelivered portion of the ore. but the court received it, and it was treated in the findings as an element in measuring the damages for which the judgment was rendered. The evidence adduced upon the trial Is contained in the bill of. exceptions.
HendersO'n, Kline & Tolles (Virgil P. Kline, of counsel), for plaintiff. Hoyt, Dustin & Kelley (A. C. Dustin, of counsel), for defendant. Before TAFT and L1JRTON, Circuit Judges, and SEVERENS, District Judge. Having stated the case as above, SEVERENS, District Judge, -delivered the opinion of the court. Although the record in this case presents the objections and exceptio-:J.s of the plaintiff in the court below in a crude and rather -defective form, we think they are sufficient to require us to review the principal questions involved in the determination of the correctness of the judgment, and, as their sufficiency for that purpose has not been controverted by the defendant, we shall not go into that subject for discussion in detail. In order to proceed to a right conclusion upon the matters in ,difference between the parties, it is necessary to ascertain what
572
FEDERAL REPORTER,
vol. 64.
Is the proper construction of .the contract, mentioned. in the foregoing statement,. of August 20, 1890, and .especially of the stipula· tion, at the end thereof, whereby the vendor reserved the right to cancel the same as to undelivered ore in case the vendee should fail to make the payments as agreed; for it is upon the construction and e:lfect of. that clause. in the contract that the controversy mainly turns. It will be convenient to consider, in the first place, what would have been the effect of the contract had that stipulation been omitted. In that case it would have been a contract simply for the safe of 10,000 tons of ore, deliverable in seven equal parts in each of the seven months named, for the price of $37,500,payable in seven equal installments,payable during those months respectively. The contract w()lUld haye been entire, and would have bound the vendor to deliver the whole amount, and the vendee to pay the whole. price. The fact that there were subordinate stipulations in regard to the dates of delivery and of payment would not break it up into separate contracts for each installment of the ore. It is sufficient to cite, upon this point, the cases of Iron Co. v. Naylor, 9 App. Cas. 434, in the English house of lords, and Norrington v. Wright, ·115 U. S. 188, 203, 204, 6 Sup. Ct. 12. And, the contract being entire, as soon as the parties had entered upon its performance by partial delivery and payment, the mere failure of the vendee to make the subsequent payments would not of. itself absolve the vendor from proceeding with the deliveries. It may be that a downright refusal to make payment, or other equivalent con· duct evincing a purpose to renounce the contract, would entitle the other party to treat the contract as abandoned, and relieve him from the obligation to proceed further in its execution. Winchester v. Newton,. 2 Allen, 492. In respect to the obligation of the vendee to accept delivery of the goods under such a contract, where the vendor fails to comply with its stipulations with regard to the time and mode 'of delivery, it was held in Norrington v. Wright, supra, that he was entitled to insist upon a continued adherence to its terms. This was because they were of the substance of the .thing contracted for. But the duty of the vendor, notwithstanding. a mere failure of the vendee to make payment of money, not evincing a renunciation of the contract, stands upon a different ground, as pointed out in that opinion, and results, also, from a comparison of the actual decision in that case with other cases distinctly involving the vendor's duty in those circumstances, among them the case of Iron Co. v. Naylor, which it recognizes as authoritative. In view of the obligation, which the vendor in this contract would otherwise have assumed, to go on with its deliveries notwithstand· ing a failure to pay, the clause was added by which it could relieve itself of that duty in case it should find it to its interest to do so. It is somewhat plausibly contended by the defendant that the right reserved to "cancel this contract for all ore not delivered at the time such default is made" was the power to obliterate the stipulations of the parties so far as they applied to the undelivered ore, the exercise of which would untie the obligation of the vendee to answer for the damages produced by his preceding
CHERRY VALLEY IRON WORKS V. It'LORENCE IRON RIVER CO.
573
failure to perform the contract, as well as the obligation of the vendor to make further delivery. But we do not think that this is the just construction of the language of that provision, or that it is the construction intended by the parties. In our opinion, it was intended to give an opportunity to the vendor, in the event of nonpayment, to stand on that breach as a justification for its refusal to deliver the ore then undelivered, and treating the contract at an end, so far as its further performance was concerned. We cannot think that it was intended that the exercise of that right was intended to be followed by the consequence o.f relieving the vendee from responsibility for the very default which was the cause of the vendor's canceling the agreement to make further de· livery. The right of the party without fault to treat the obliga· tion to go further as at an end by reason of the nonperformance of the other party is sometimes spoken of in judicial opinions as a right "to cancel the agreement," whereupon the right would accrue to the party not in fauIt to sue for his damages. We think that the word must be deemed to have been used in that sense here. But the plaintiff contends that the letter of June 15th was in itself an unequivocal rescission of the contract as far as it related to the undelivered ore, and put an end to the mutual obli· gations of the parties with respect to it. But it professed to be the assertion of the right secured by the contract, and upon the construction of the contract itself which we think is the right one the exercise of that right would not be followed by such consequences. Aside from that consideration, we do not think the letter bears the construction which the defendant puts upon it. An absolute rescission implies that the parties are to be restored to their former position, and this would involve, among other things, the repayment of the excess of purchase price then in the hands of the vendor. This was not offered or proposed by it in the let· ter, and the purpose was plainly indicated to hold on to all the vendee's obligations. This put such a limit upon the effect of the language used as to prevent it from operating as a rescission in the technical meaning of that term. In the case of Lumber Co. v. Bates, 31 Mich. 158, there was a contract for the sale of a quan· tity of lumber, to be thereafter delivered, at an agreed price, part of which was paid down. The lumber was not delivered as agreed, and, after much procrastination, the vendees addressed a letter to the vendors, in which, after reciting the terms of the agreement, and the vendors' breach thereof, they go on to say: "We shall not, therefore, now accept or receive said logs on the contract, and shall look to· you for the money already paid you by us, and interest thereon, and the note of ours you now hold, and for our damages sustained by your failure to perform the contract according to its terms."
The vendees then sued to recover back the consideration which had been paid, upon the ground that the contract had been rescinded, and recovered judgment. But, upon awrit of error to the supreme court, that court said of the plaintiff's oontention: "They could not, in any event, rescind in part, or hold it valid for one purpose and void for another. They must rescind entirely, or not at all. But
574
vol. 64,
here,a.ttwdeclaring thei!: intention to rescind, they say, further,'we shall look for our damages sv,stainell' by your the contract to its terms.' 'There being no rescission estabIlshed in the present caSe, tllejudgment must be reversed." I, ··
"I ,j;i'atisfied that th'il, letter cannot be treated as a. rescission, even if the pll.rt(es .could then have rescinded. Taken altogether, it is rather an assertion of a breach of the contract, and of such delay as would justify a refusal to accept the lumber agreed to be delivered, by reason of the breach, and a claim of damages, instead of a return of the consideration."
And'.'JtidgeCamphell, in a concurring opinion, said of the letter:
am
That case bears a striking analogy to the present case, upon that aspect of the controvers(Y. This conclusion leads to the result that, upon the exercise of the right of cancellation provided bY'the contract after a failure to make the agreed payment, the further performance of it was abandoned, and the aggrieved party had the right to pursue its remedy for the damages'sustained by it in consequence of the breach of the contract which was the cause of its abandonment. The plaintiff failed to make the"December payment in the manner promised in its agreement, but remitted its notes instead of cash. '.Dhis was at first objected toby the defendant, bUt, upon an agreement of the plaintiff to take up the notes during that month, they were retained. They were not so paid. But they were retained by the defendant, negotiated by it, and afterwards paid by the plaintiff. We think the defendant, retaining and negotiating the notes, was not entitled to treat the plaintiff as in default in respect to the December payment. But the default in the January payment was absolute, and justified the defendant in resorting to the privilege reserved, of refusing to go on with the deliveries on account of that default. Its purpose to do this was distinctly indicated on the 27th of January, when it refused to deliver ore as requested. That refusal could only be justi. :fled as an exercise of its election to proceed no further on the contract. It is true it offered, to surrender the position it had assumed, if the other side would make the defaulted payments, but correspondence on the subject was fruitless, and no agreement was ever reached thereafter in respect to it, and on May 15th following it finally gave notice that negotiations were at an end, and, in effect, that it adhered to the proposition that the contract would be treated as canceled. The defendant stood upon the ground it had taken in January, and it must betaken to have elected to treat the contract as broken by the default in making the payment due in .January. Upon this view of the nature of the contract, the admission of the letters which passed between the parties between the 29th of January and 15th of June, if erroneous, was harmless, for 'they would not change the contract orthe rights and obligations of the parties. The position of the parties, therefore, was this: The plaintiff was entitled to recover the amount which it had paid in excess of the contract price of the quantity of ore actually delivered; and the de. fendant was entitled to recover, by way of counterclaim, the damages which it had sustained from the plaintiff's breach of the contract which had, on account of such breach, been "canceled" by the de. fendant. As to the amount of excess of payment by the plaintiff,
CHERRY VALLEY IRON WORKS V.
IRON RIVER 00.
575-
there is no dispute. In regard to the measure of defendant's damages, we think the court below erred in· adopting a rule which was not applicable. The defendant, entertaining an erroneous conception of the means which it was entitled to adopt to fix the amount of its damages, gave notice, in its letter of June 15th, of its purpose to sell the undelivered ore for account of the plaintiff, and hold the latter for the difference between the price realized from the sale and the contract price; and this purpose it carried into effect on July 31st, nine days after the suit was commenced. The sale in this case was of goods to be taken from a mass. The subject of the bargain was not, therefore, identified at the time when it was made. It is true that the goods might afterwards be identified by a separation from the mass, and the appropriation, by the vendor, of the portion thus identified, to the contract. Blackb. Sales, 128; Benj. Sales, 358 et seq.; Claflin v. Railroad, 7 Allen, 341; Bank v. Bangs, 102 Mass. 291. This is because his authority to make the appropriation is implied in the contract. If the subject-matter is identified when the contract is made, the title passes to the vendee, in the absence of controlling stipulations. When the subject-matter is subsequently identified by its appropria. tion to the contract, the title passes at the time of such appropriation. But when there has at no time been identification of the subject, the title remains in the vendor. In those cases where the title has passed before the contract is broken, and the rights of the parties have been converted into claims for damages arising from the breach, the nature and kind of remedies to which the vendor may resort is the subject of much controversy in the opinions of the courts. There is high authority for the proposition that the vendor, in such a case, may, among other remedies, by virtue of a species of lien for the purchase price, sell the goods as those of the vendee, and hold the latter for the difference between the price obtained and the contract price. This was the remedy resorted to here. It is not necessary for us to decide whether the vendor has this remedy in the class of cases just mentioned. It is clear that this case does not belong to that class. Here, the title never passed, and the goods at all times remained the property of the vendor, subject to any disposition it might be pleased to make of them, until it finally sold them on the market to other parties. 'fhe implied authority of the vendor to segregate the goods and appropriate them to the contract had long previously expired. In such cases the rule is general, if not universal, that the measure of the damages which the vendor may recover is the difference between the contract price and the market price at the time fixed by the contract for delivery. 2 Sedg. Dam. (8th Ed.) § 753; Boorman v. Nash, 9 Harn. & C. 145; Phillpotts v. Evans, 5 Mees. & W. 475; Ripley v. "McClure, 4 Exch. 345; Leigh v. Paterson, 8 Taunt. 540; Brownlee v. Bolton, 44 Mich. 218, G :No W. 657; Keller v. Strasberger, 90 N. Y. 379; Zuck v. McClure, 98 Pa. St. 541. In the present case the parties had, by mutual concurrence, postponed part of the October, November, and December deliveries, but to no definite time, and the parts of the are which had been thus passed over, at the date of the cancellation, were then due. The
J'EDERAL REPORTER,
being those for January, February, March, and in any part of each of such months, and it would that the average value during the month would be the just basis of comparison for the market price. The defendant elected on the 29th of January, 1891, to treat the contract a!!l broken. That was the inevitable inference to be drawn from its refusal to go on with it. And, having once made its election, was bound by it, unless the parties should thereafter substitute some new agreement, which, as we have already said, was not done. The proceeding of the defendant in making the,sale on July 31st of a quantity of ore equal to the remaining portion thereof, for ac' count of the plaintiffs, was wholly unauthorized, and proof thereof was immaterial. Nor was it admissible to prove the actual market value of the ore. It was several months later than the time to which such proof would be relevant, and it is distinctly shown that the price was steadily sinking during that period. The date was too remote to furnish any reliable basis for estimating the value of the ore' at the dates when it was deliverable. But it further appears that the court made the plaintiff responsible for this sale ill July, and made it the basis of the defendant's recovery. It follows, it'om what we have.said, that this was error. There is no finding in regard to the value of the ore at the time fixed by the contract for the deliveries, and we have not the data for ordering the proper judgment. The judgment of the circuit court will therefore be reversed, with directions to award a new trial. In re CERTAIN MERCHANDISE. (Circuit Court. D. Massachusetts. No. 188. APPEAL-REVIEW UNDER CUSTOMS ADMINISTRATIVE ACT-PETITION-DISMISSAL.
November 23. 1894.)
Though the customs administrative act of 1890 (section 15). providing for an appeal. requires seeurity for costs on the original application for review by the importer. and the practice of the court conforms thereto. an application filed when the statute was new. and when there was no express rule of court defining what the security should be. and prosecuted in good faith by counsel. who did not understand that the statute required security at the outset, will not be dismissed because security was not given when the application was made. if the ordinary cost bond in the sum of $50 is filed within the time named in the ruling on the motion to dismiss.
Petition by Schoellopf, Hartford & Maclagan, Limited, for review under the customs administrative act of 1890. Heard on motion by the government to dismiss. Motion denied on conditions. Josiah P. Tucker, for petitioner. Wm. G. Thompson"Asst. U. S. Atty. ALDRICH, District Judge. This is a petition by the importer for review under what is known liB the "Customs Administrative Act of 1890," and there is no security for costs. Section 15, providing for review and appeal, requires that "on such original application